Cunnery Meadow Play Area Work to begin July 8th

Cunnery Meadow Play Area  Work to begin July 8th

They will be spending the first week removing the old equipment from site. This will involve the delivery of containers to be sited at the Cunnery Meadow end of the field on Monday morning.
On Tuesday the security fencing will be delivered and erected on site, and on Wednesday the dismantling of the play area will begin. This will involve the delivery and removal of skips to site.
It is expected that the dismantling work will be completed on July 17th. The site will then be made secure until the new equipment arrives to be installed on August 5th.
Access to site will be from Cunnery Meadow, the contractors will be accessing site with deliveries etc during normal working hours; 8:30 to 4:30 Monday to Friday.
The contractors will aim to minimise any disruption, however if you experience any problems or have any concerns please contact Clayton-le-Woods Parish Council on 01257 264854 or email projects@claytonlewoodsparishcouncil.org.uk.